If you would like to download this document, click on the PDF button.
Checklist for Reviewing and Analyzing CPM Schedules
- Has an electronic copy of the CPM schedule been provided to the reviewer?
- Is the schedule complete?
- Is the schedule sufficiently detailed to make it useful?
- Are all submittals and submittal reviews included as separate activities?
- Are procurement, fabrication and delivery times included as activities on the schedule?
- Are procurement, fabrication and delivery times reasonable and achievable?
- Are realistic milestones or windows for delivery of owner-furnished equipment and materials included in the schedule?
- Are required start-up and testing activities included in the schedule?
- Are start-up and testing activity durations realistic and achievable?
- Is responsibility for each activity assignable to one entity?
- Are activity durations reasonable?
- How were activity durations estimated: company historical data, subcontractor input, productivity calculations, guesstimate?
- Have any float suppression techniques been utilized: e.g. preferential logic, special lead/lag logic restraints?
- Are activity relationships complete?
- Are activity relationships valid?
- If the contract requires resource-loading, have the requisite costs, and/or labor and equipment been included? Compare resource-loading with duration to determine if both are logical, reasonable and mutually supportable.
- Are the project calendars correct?
- Is the overall schedule duration within the contract completion time?
- Are contractual milestones met?
- Are contract-described schedule constraints (construction sequences, on-going operating constraints) included in the schedule?
- Are there any artificial, non-contractual date constraints?
- Are schedule activities adequately coordinated with other (multiple) prime contractor schedules, if applicable?
- Is the critical path reasonable?
- Are there multiple critical paths?
- What activities are near critical?
- How does the work flow?
- Are there conflicts between concurrent activities?
- Is there an excessive amount of work at any time?
- Are there sufficient resources to support the planned construction operation?
- Can subcontractors and suppliers meet the planned construction schedule?
- Are any activities scheduled to be performed out of season?
- If the schedule reflects an early completion date, is the early date reasonable and achievable?
- If there is an activity for "substantial completion", does it reflect the definition of "substantial completion" in the contract and is it realistic and fair to all?
Management Resources
- Agenda for Pre-Construction Meeting
- Checklist for Evaluating a Differing Site Condition Claim
- Checklist for Preparing for Arbitration
- Checklist of Scheduling Specifications
- Checklist for Reviewing and Analyzing CPM Schedules
- Checklist for Reviewing and Analyzing CPM Schedule Updates
- Checklist of Project Documentation
- Documents Required for Claims Analysis
- Extended Field Overhead Checklist
- Extended Home Office Overhead Checklist
- Importance of Pre-bid RFI System
Twitter Updates
Dan
danfauchier
- feed:
- follow:
- web:
- location:California
- updates:207
- followers:57
Loading...
Last 2 tweets in past 30 days from danfauchier:
People talking about '@danfauchier':
