Extended Field Overhead
Extended Field Overhead is based on ACTUAL costs as
documented by invoices, timesheets, accounting printouts, etc. These must be
accurate and auditable.
The best procedure is to collect the source documents –
invoices, timesheets, accounting printouts, etc. – organize them as shown
below, summarize the information and calculate a calendar day rate, then attach
the source documents as exhibits to the calculations.
If forward pricing Extended Field Overhead, utilize a
calendar day average of a representative period, which may be the project period
to date or only the most recent months, if there is substantial difference
between various phases of the project. If pricing the Extended Field Overhead at
the end of the delay, utilize ACTUAL costs for the period.
Organize the presentation of Extended Field Overhead into five sections:
Extended Field Office
- Office trailers
- Office furniture
- Office equipment including copy and fax machines, computers, etc.
- Communication equipment including phone company and ISP charges and 2-way
radios
- Office utility bills (electricity, gas, water)
- Office supplies
- Office janitorial
- Project photography and videography
Extended Field Supervision (salary, benefits, taxes, housing and expenses
reimbursed)
- Project Manager (if routinely costed to the job, not carried as G&A)
- Project Engineer (if routinely costed to the job, not carried as G&A)
- Project Scheduler (if routinely costed to the job, not carried as G&A)
- Superintendent
- General Foremen
- Field office clerical
Extended Field Labor (these may be estimated if time is not recorded in
detail – if estimated, explain in detail how and why you calculated these
amounts)
- Safety crews (flaggers, cone maintenance, fence maintenance)
- Security personnel
- General cleanup crews (site cleanup, street cleanup)
- Survey and staking crews
- Equipment maintenance crews (if routinely costed to the job, not carried
as G&A)
Extended Equipment (rental costs or equivalent for owned equipment)
- Storage trailers
- Portable toilets
- Safety equipment (fences, K-rail, cones)
- General cleanup supplies (site cleanup, street cleanup)
- Support equipment (forklifts and other general equipment not tied to bid
items)
- Water storage and trucks and de-watering equipment
- Winterizing, snow removal, heaters, air conditioners
- Staff equipment (pickup trucks for PM, Superintendent, General Foremen)
- Fuel, oil and maintenance for equipment
Summary of Extended Field Overhead
- Present the subtotals of the above four sections
- Summarize these into a unified cost per calendar day for Field Extended
Overhead
CONTRACTORS: Utilize this format in preparation of your change order or
claim.
OWNERS: Request that the contractor utilize this format in preparation of
the change order or claim.