Documents Needed for Claims Analysis
Contract documents
Prime Contract (Owner – GC)
All Amendments
All Change Orders and Change Order Requests
Copy of approved change orders
Include breakdown of labor, material, equipment
Copy of requested, unapproved change orders and current status
Include breakdown of labor, material, equipment
Include all correspondence exchange regarding each denied or pending
change order
Relevant subcontracts
Specifications including
General Conditions
Special Conditions
Contract drawings including
Addenda
Architect’s Clarifications
Sketches
Bid documents
Bid work papers (if relevant to this issue)
Submittals and shop drawings related to this issue
RFIs and responses
Include the total number of RFIs on the project, number related to this
issue, number involving your organization only (for subcontractors)
Include number of labor hours expended for contract work vs. change work
Your organization
All organizations performing work on the project (if relevant)
CPM Schedules
Original approved baseline CPM
All updates, especially the most recent update
Include narratives or explanations attached to the updates
Any 2-week or 3-week look-ahead bar charts
Any recovery schedules, acceleration schedules
Project logs
Submittal log
RFI log
Change order log
Backcharge log
Correspondence log
Phone logs
Email logs (if any)
Access to any electronic or internet project management systems, for
example:
Prolog
Expedition
Constructware
Citadon
Meeting minutes, including
Meetings between GC, Owner, Designer
Meetings with subcontractors
"Special topic" meetings including:
Scheduling meetings
RFI meetings
All relevant correspondence between the parties, including
Letters between GC and owner
Letters between GC and subs
Daily reports and diaries
GC’s superintendent’s daily reports
Subcontractors daily reports
Inspector’s or QC daily reports
Photographs, video tapes
and other visual media related to this issue
(if none exist, begin documenting them now)
Internal memoranda
Internal memoranda (within your organization)
Notes of verbal conversations
Memos to file
Memos of phone conversations
Cost Code and budget reports
Weekly
Monthly
Possibly: relevant daily time sheets
Include identification of hours spent on acceleration or disruption and
delay
Lists of and receipts for equipment used
(if relevant to the issue)
Owned
Rented
Identify escalation related to this issue
Lists of and receipts or invoices for additional or substituted materials
(if relevant to this issue)
Include any quantity calculations or take-offs
Identify escalation related to this issue
Schedules or lists of labor trades utilized
(as relevant to this issue)
Indicate entity supplying each labor trade (GC or sub)
Include breakdown of base rates, benefits, taxes, workers comp, insurance,
union benefits, etc.
Identify escalation related to this issue
Existing or previous claims or requests for equitable adjustment (REA)
Project Manager’s brief project and issue HiSTORY
(factual story form)
Include major events and relevant minor incidents
Describe the claim you envision (or have filed), including elements of the
claim you anticipate: delay, disruption, acceleration, inefficiency,
suspensions and stop-work orders, added or diluted supervision
Be factual, include dates, names, if possible cross reference to actual
documents which can be looked at while reviewing the narrative (NOTE: to the
degree you do not do this, the consultant will likely have to do this.)
Bonds
required and bond costs, as relevant
If claiming extended overhead, provide:
Actual field costs during the extended period (include accounting
printouts, invoices, receipts, etc.), including:
Supervision above general foreman
Project manager costs (if your accountant costs these to the project,
otherwise they are part of home office overhead)
Trailer rents (office and storage)
Temporary power to trailers
Janitorial and other services to trailers
Additional costs of office equipment and supplies
Extended safety and fencing costs
Additional layout expense (beyond that in the bid)
Audited financial reports for your organization showing total revenues,
revenues for this project, G&A (general and administrative expenses) for
all years during which this project is/was open
Any other documents you feel might be useful in understanding and preparing
the analysis or claim