Documents Needed for Claims Analysis
April 22nd, 2008 by admin, under Uncategorized. No Comments
Documents Needed for Claims Analysis
- Contract documents
- Prime Contract (Owner – GC)
- All Amendments
- All Change Orders and Change Order Requests
- Copy of approved change orders
- Include breakdown of labor, material, equipment
- Copy of requested, unapproved change orders and current status
- Include breakdown of labor, material, equipment
- Include all correspondence exchange regarding each denied or pending change order
- Copy of approved change orders
- Relevant subcontracts
- Specifications including
- General Conditions
- Special Conditions
- Contract drawings including
- Addenda
- Architect’s Clarifications
- Sketches
- Prime Contract (Owner – GC)
- Bid documents
- Bid work papers (if relevant to this issue)
- Submittals and shop drawings related to this issue
- RFIs and responses
- Include the total number of RFIs on the project, number related to this issue, number involving your organization only (for subcontractors)
- Include number of labor hours expended for contract work vs. change work
- Your organization
- All organizations performing work on the project (if relevant)
- CPM Schedules
- Original approved baseline CPM
- All updates, especially the most recent update
- Include narratives or explanations attached to the updates
- Any 2-week or 3-week look-ahead bar charts
- Any recovery schedules, acceleration schedules
- Project logs
- Submittal log
- RFI log
- Change order log
- Backcharge log
- Correspondence log
- Phone logs
- Email logs (if any)
- Access to any electronic or internet project management systems, for example:
- Prolog
- Expedition
- Constructware
- Citadon
- Meeting minutes, including
- Meetings between GC, Owner, Designer
- Meetings with subcontractors
- “Special topic” meetings including:
- Scheduling meetings
- RFI meetings
- All relevant correspondence between the parties, including
- Letters between GC and owner
- Letters between GC and subs
- Daily reports and diaries
- GC’s superintendent’s daily reports
- Subcontractors daily reports
- Inspector’s or QC daily reports
- Photographs, video tapes and other visual media related to this issue (if none exist, begin documenting them now)
- Internal memoranda
- Internal memoranda (within your organization)
- Notes of verbal conversations
- Memos to file
- Memos of phone conversations
- Cost Code and budget reports
- Weekly
- Monthly
- Possibly: relevant daily time sheets
- Include identification of hours spent on acceleration or disruption and delay
- Lists of and receipts for equipment used (if relevant to the issue)
- Owned
- Rented
- Identify escalation related to this issue
- Lists of and receipts or invoices for additional or substituted materials (if relevant to this issue)
- Include any quantity calculations or take-offs
- Identify escalation related to this issue
- Schedules or lists of labor trades utilized (as relevant to this issue)
- Indicate entity supplying each labor trade (GC or sub)
- Include breakdown of base rates, benefits, taxes, workers comp, insurance, union benefits, etc.
- Identify escalation related to this issue
- Existing or previous claims or requests for equitable adjustment (REA)
- Project Manager’s brief project and issue HiSTORY (factual story form)
- Include major events and relevant minor incidents
- Describe the claim you envision (or have filed), including elements of the claim you anticipate: delay, disruption, acceleration, inefficiency, suspensions and stop-work orders, added or diluted supervision
- Be factual, include dates, names, if possible cross reference to actual documents which can be looked at while reviewing the narrative (NOTE: to the degree you do not do this, the consultant will likely have to do this.)
- Bonds required and bond costs, as relevant
- If claiming extended overhead, provide:
- Actual field costs during the extended period (include accounting printouts, invoices, receipts, etc.), including:
- Supervision above general foreman
- Project manager costs (if your accountant costs these to the project, otherwise they are part of home office overhead)
- Trailer rents (office and storage)
- Temporary power to trailers
- Janitorial and other services to trailers
- Additional costs of office equipment and supplies
- Extended safety and fencing costs
- Additional layout expense (beyond that in the bid)
- Audited financial reports for your organization showing total revenues, revenues for this project, G&A (general and administrative expenses) for all years during which this project is/was open
- Actual field costs during the extended period (include accounting printouts, invoices, receipts, etc.), including:
- Any other documents you feel might be useful in understanding and preparing the analysis or claim